This is a letter from Robert McNeil about our time table concerning the dam. Sounds great! Remember that we lost close to 5 feet of water last season, so 2 feet shouldn't be all that bad before Memorial day. We should fill up quite fast at that point.
I wanted to give everyone an update on the Sugden Dam
repairs. We are purchasing the new lift gate directly (separately from
the installation contract) to expedite the construction schedule and save on
the contractor’s markup. Plans are available to potential bidders through
our Engineer (PARE Corp.) and will be available for viewing here at the U&F
office.
Our proposed schedule is as follows:
Dam Repairs
Lift Gate Supply
Notice to Central
Register
March 1, 2011
N/A
Publish in Central
Register March 9,
2011
N/A
Gate RFP
Invitations
N/A
March 4, 2011
Plans
Available
March 14,
2011
March 4, 2011
Pre-bid
Conference
March 17,
2011
N/A
Bids
Due
March 31,
2011
March 11, 2011
Contract
Award
April 7,
2011
March 18, 2011
Gate Fabrication (8
weeks)
N/A
May 13, 2011
Contract
Completion
May 27, 2011
May 13, 2011
With any luck we will be in service for Memorial Day
Weekend.
NOTICE:
Please keep in mind that the lake level will be drawdown again (two feet below
spillway) to facilitate proposed repairs to the spillway.